Improving Productivity through Mistake-proofing of Construction Processes

12Citations signalées — pas une note de qualité
0Institutions déclarées
0Pays d’affiliation déclarés

Résumé fourni par la source

Construction defects are always the key concern of the construction industry. Research shows that, the estimated costs of rework for residential construction are almost equal to 4-5% of contract value. One of the successful devices in lean production to eliminate waste caused by errors is 'mistake-proofing' or 'Poka-yoke'. Mistake-proofing is one of the effective approaches that prevents inadvertent errors and helps workers to be mistake-proof and does not allow defective products to flow to next processes. In this paper, application of Poka-yoke to construction industry is investigated. The results show that the construction operations have high potential of mistake-proofing, and therefore the application of Poka-yoke devices can finally lead to drastic promotion in construction industry. At last section, a case study related to the simple operation of a trolley hoist also conducted to evaluate productivity improvement due to the process mistake- proofing in practice.

Ce résumé expose les affirmations des auteurs. BNTIC ne l’interprète pas comme une validation indépendante des résultats.

Contrôle bibliographique ouvert

Aucun DOI disponible pour le contrôle Crossref.

Sujets associés

BIM and Construction IntegrationConstruction Project Management and PerformanceOccupational Health and Safety Research

BNTIC News n’est pas le producteur de ces données. Recherche à la demande dans Crossref et Europe PMC, sans clé ; OpenAlex reste optionnel. Aucun service payant requis, aucune réponse conservée. Sources et limites.