Schedules: MITICA plan is being updated after recent developments/decisions on 1 MV insulating transformer reconstruction. Quality: further revision of Quality Plan ongoing, together with some procedures. Internal quality audits have started with primary goal to gather feedback and improvement opportunities. Third parties: …
2022
report
OpenAlex
V. Toigo, D. Marcuzzi, G. Serianni, Boldrin M. et autres
Annual report completed and transmitted to the ITER NBTF RO Intermediate report Q1 in preparation NAC meeting held in three days: 9, 13, 20 May Visit of WPrIO PL on 16th and 17th of May SC meeting in preparation Procurement contract for …
2022
report
OpenAlex
V. Toigo, D. Marcuzzi, G. Serianni, Boldrin M. et autres
Discussion ongoing with IPP, regarding possible collaboration on future joint experiments on BUG and ELISE, in particular integrating additional diagnostics (e.g. emittance scanner).
2022
report
OpenAlex
V. Toigo, D. Marcuzzi, G. Serianni, Boldrin M. et autres
SPIDER and MITICA plan being reviewed, in view also of the preparation of AWP2023. Updated versions of the SPIDER and MITICA schedules will be made available in view of the next NAC meeting scheduled for October. The RoD of the SC has …
2022
report
OpenAlex
V. Toigo, D. Marcuzzi, G. Serianni, Boldrin M. et autres
Annual report completed, under final revision by RFX director.
2022
report
OpenAlex
V. Toigo, D. Marcuzzi, G. Serianni, Boldrin M. et autres
A progress meeting with DAs was held on 21st of June. The aim is to keep the DAs updated on progress and in particular on lessons learned.
2022
report
OpenAlex
V. Toigo, D. Marcuzzi, G. Serianni, Boldrin M. et autres
NAC and SC meetings held in the last period, finalization of minutes and actions ongoing.